Agenda Item

13-1857 Approval by the Board of Education of Change Order No. 1 to Construction Contract with Turner Construction/ADCO JV., Oakland, CA, for the latter to provide 12 inch extension on PG&E vaults to increase it from 6 feet to 7 feet deep, per PG&E review*, in conjunction with the La Escuelita Eductional Center Phase 1 Increment 2 Project in the amount of $567,475.00, increasing the Agreement from $36,000,000.00 to $36,567,475.00. All other terms and conditions of the Agreement remain in full force and effect. --------------- * Contractor had to modify the vault depth; off haul of existing concrete foundation; additonal material required during installation of PG&E primary conduit.