Meeting Time: June 25, 2014 at 5:00pm PDT

Where: 1050 Second Avenue Oakland, CA 94606-2291

The online Comment window has expired

Agenda Item

14-1482 Approval by the Board of Education of Resolution No. 1314-1150 - Award of Bid and Construction Contract between District and Stronger Building Services, Hayward, CA, for the latter as the lowest responsive, responsible bidder and rejecting all other bids, if any, to provide replacement of the built-up roofing membrane, gutters, and downspouts for the three buildings on campus; select eaves will be replaced where they have been damaged by dry-rot; a new roofing system will be a single-ply TPO, new sheet metal gutters and downspouts in conjunction with the Rudsdale Academy Roof Replacement Project for the period commencing with work to be completed within Sixty (60) consecutive calendar days from the date specified in the District's Notice to Proceed, with all work being completed by August 16, 2014, with all work being completed by August 16, 2014, in the amount of $216,715.00.