13-2289 Approval by the Board of Education of Amendment No. 2, Purchase Order between District and Intelli-Tech, Pleasanton, CA, for the latter to provide electrical services to terminate the EPO wiring and assist in testing the EPO System in the Server Room; in addition, Contractor is to perform an additional fan pressurization tests of the Server and HVAC rooms to validate the rooms are sealed adequately by others in conjunction with the La Escuelita Educational Complex Project, in an additional amount not to exceed $3,329.00, increasing the Contract not to exceed amount from $37,318.00 to $40,647.00 and extending the Contract date of June 14, 2011 through August 31, 2012 to December 31, 2013. All other terms and conditions of the Contract remain in full force and effect.