Agenda Item

12-3096 Approval by the Board of Education of Resolution No. 1213-0044 - Approval of Increased Project Budget Expenditure and Amendment of Lease Back Agreements Pertaining to the Lowell Modernization Project ("Project") #06004 in the amount for $750,000.00 increasing the Guaranteed Project Cost (GPC), for reasons stated herein, from $14,297,443.00 to $15,047,443.00