Meeting Time: August 27, 2025 at 4:00pm PDT

Disclaimer:

Would you please share with us your view(s) or position(s) on a meeting agenda item? Your comments and information will become part of the public record of this web site, which is external to the legislative meeting minutes. If you do not wish your personal information included in the public record of this site, please omit completion of that field.


Agenda Item

L.-3 25-1872 Approval by the Board of Education of Change Order No. 1, Agreement Between Owner and Contractor, by and between the District and RK Roofing & Construction, Inc., San Leandro, CA, for the latter to replace the dry-rotted roof deck lumber, demolish the insulation within HVAC equipment, tapered insulation in valleys and walkways; install new ISO insulation in the valleys, HVAC wells, and walk paths; hire a structural engineer, treat dry-rotted structural beams, and install six structural plates to support the beams, as outlined in PCOs No. 1 to No. 3 for the Highland Child Development Center Roof Replacement Project, in the not-to-exceed amount of $320,337.28, increasing the Agreement price from $297,000.00 to $617,337.28. All other terms and conditions of the Agreement remain in full force and effect.

Hello Guest User

Please enter your information or Sign In


   Oppose     Neutral     Support    
1000 of 1000 characters remaining