Agenda Item
T.-4 24-0603 Approval by the Board of Education of a Construction Agreement Between Owner and Contractor by and between the District and Diversified Flooring Services, Inc., Millbrae, CA, for the latter to demolish existing flooring and replace it with VCT tile vinyl flooring in buildings 30 and 40 hallways at Edna Brewer Middle School, as described in the proposal dated March 7, 2024, attached to the Agreement as Exhibit A, incorporated herein by reference as though fully set forth, in the lump sum amount of $39,130.00, with the work commencing on April 11, 2024, and being completed by August 31, 2024.