Agenda Item
E.-3 23-1792 Approval by the Board of Education of an Agreement Between Owner and Contractor by and between the District and G & G Builders, Inc., Livermore, CA, for the latter to provide installation of tiles, demolition to existing play structure, Playmatting, tetherball poles, and basketball hoops, more specifically described in Bid Form Document 00 31 01, incorporated herein by reference as though fully set forth, for the Esperanza at Stonehurst Elementary School Site Improvements Project, in the amount of $176,134.00, which includes a general contingency allowance of $21,500.00, as the lowest responsive bidder, with the work performed on September 14, 2023, and completed within thirty days (30), with an end date of October 13, 2023.