T.-24 23-1523 Approval by the Board of Education of Agreement Between Owner and Contractor by and between the District and Alaniz Construction, Inc., Fremont, CA, for the latter perform construction services to provide a seal coating, crack filling to clean and seal cracks with crack filler prior sealer, Seal Coat with Latex, sweep designated areas of asphalt pavement free of dirt/aggregate, further described in the Proposal, dated March 20, 2023, which is attached as Exhibit A to the Agreement, for the Lockwood STEAM Elementary School Site Improvements Project, in the total amount of $57,454.00, with the work scheduled to commence on July 1, 2023, and scheduled to last until October 12, 2023.