Agenda Item

U.-5 23-0553 Approval by the Board of Education of Change Order No. 1, Agreement Between Owner and Contractor by and between the District and DecoTech Systems, Walnut Creek, CA., for the replacement of 7 analog cameras locations initially scheduled for repair with IP cameras for consistency of quality, as determined during review of construction by owner and contractor, with credit provided for materials and labor associated with analog repair scope, with the balance of the IP Cost of Replacement (COR) being $6,082.52, increasing the Agreement not to exceed amount from $240,500.00 to $246,582.52, for the Oakland High School Security Improvement Project. All other terms and conditions of the Agreement remain in full force and effect.