T.-4 22-2803 Approval by the Board of Education of Agreement Between Owner and Contractor by and between the District and G & G Builders, Inc., Livermore, CA, for the latter to provide site preparation required for the installation of equipment and matting on site to be done by Contractor, for the Centro Infantil Child Development Center Play Matting and Play Structure Project, in an amount not to exceed $83,995.00, which includes a contingency allowance of $13,000.00, as the lowest responsive, responsible bidder, with the work anticipated to commence on January 23, 2023, and scheduled to last for thirty days (30), with an anticipated ending on February 21, 2023.