Meeting Time: September 14, 2022 at 4:00pm PDT
The online Comment window has expired

Agenda Item

T.-7 22-1858 Approval by the Board of Education of Amendment No. 2, Agreement for Architectural Services by and between the District and Multistudio (formerly Gould Evans), San Francisco, CA, for the latter to provide additional design and architectural services to change the mechanical system from a 4-pipe hydronic system and radiant floors to dedicated rooftop package units serving individual classrooms, as described in the Proposal dated July 7, 2022, attached to this Amendment as Exhibit A, for the Laurel Child Development Center Replacement Project, in an additional not-to-exceed amount of $55,776.00, increasing the Agreement's not-to-exceed amount from $847,100.00 to $902,876.00. All other terms and conditions of the Agreement remain in full force and effect.