V1.-5 22-1448 Approval by the Board of Education of Agreement Between Owner and Contractor by and between the District and G & G Builders, Inc., Livermore, CA, for the latter to provide removal of existing playstructure on site: clear away debris; slurry seal to repair asphalt; install new playstructure and Softiles for matting; provide utility locations and services where needed, for the East Oakland Pride Elementary School Playmatting & Structure Project, in the amount of $596,516.00, which includes a contingency allowance of $12,000.00, as the lowest responsible, responsive bidder, with the work anticipated to commence on June 23, 2022, and scheduled to last for ninety days (90), with an anticipated ending of September 20, 2022.