Meeting Time: June 22, 2022 at 4:00pm PDT
The online Comment window has expired

Agenda Item

V1.-4 22-1447 Approval by the Board of Education of Change Order No. 1, Agreement Between Owner and Contractor by and between District and Redgwick Construction Company, Oakland, CA ("Contractor"), crediting District for deduction of the cost of trellises delivered in error, for the Markham Elementary School Playmatting & Accessibility Project, in the amount of $9,174.64, reducing the Agreement amount from $419,500.00 to $410,325.36 and for a time extension of the Agreement by 94 days, from August 26, 2021, through November 23, 2021 to April 12, 2022. All other terms and conditions of the Agreement remain in full force and effect.