V1.-2 22-1282 Approval by the Board of Education of Agreement Between Owner and Contractor by and between the District and Redgwick Construction Company, Oakland, CA, for the latter to provide removal of existing playstructure on site and clear away debris, use a slurry seal to repair asphalt, install new playstructure and Softiles for matting and provide utility locations services where needed for the Madison Park Academy Playmatting & Play Structure Project, in the lump sum amount of $326,000.00, which includes a contingency allowance of $12,000.00, as the lowest responsive, responsible bidder, with the work scheduled to last for Ninety (90) Calendar days, with an anticipated start date of June 23, 2022, and end date of September 20, 2022.