Agenda Item

V1.-1 22-0674 Approval by the Board of Education of Agreement Between Owner and Contractor by and between the District and Native Soil, Inc, Oakland, CA, for the latter to design, furnish and install new irrigation system for the Garden area which will be separate from the site Landscape system; and install 3 Trench drains at the Greenhouse and 1 drain at the Sink Enclosure, for The Center New Irrigation System Project, in the amount of $55,000.00, which includes a contingency of $9,500.00 to pay any additional amounts to which the Contractor may be entitled under the Contract Documents other than special allowances, with the work anticipated to commence on April 14, 2022, and scheduled to last for ninety (90) days, with an anticipated ending of July 12, 2022.