Agenda Item

V.-8 21-2695 Approval by the Board of Education of Change Order No. 1, Agreement Between Owner and Contractor by and between the District and Everlast Development, Inc., Oakland, CA, providing credit for remaining unused Contingency Allowance for the Carl Munck Elementary School Vegetation Fire Management Project, as a deductive change in the amount of $450.00, reducing the Agreement price from $9,800.00 to $9,350.00, providing a time extension of 86 days, changing the Agreement term from July 26, 2021 through August 31, 2021 to November 25, 2021. All other terms and conditions of the Agreement remain in full force and effect.