V1.-1 21-2089 Approval by the Board of Education of Change Order No. 1, Agreement Between Owner and Contractor - District and Mar Con Builders, Oakland, CA, for reconciliation of unused allowance for the Piedmont Elementary School Playmatting Installation Project, as a deductive change in the amount of $1,492.00, reducing the contract price from $192,000.00 to $190,508.00, and an adjustment to Contract Time In This Change Order: 271 Calendar Days, extending the term from September 11, 2020 through December 15, 2020 to September 12, 2021. All other terms and conditions of the Agreement remain in full force and effect.