V1.-10 21-1837 Approval by the Board of Education of Construction Management Agreement between the District and Layas Partnership, Oakland, CA, for the latter to provide Construction Management Services. Layas will be responsible for the construction of Castlemont High School Field and Bleachers Project and the management of the monitoring activities performed by Ninyo & Moore with oversight by the Department of Toxic Substances control at LaEscuelita Education Center, for the Facilities Planning and Management Project, in the not-to-exceed amount of $48,720.00, as the selected consultant, with work scheduled to commence on July 1, 2021, and scheduled to last until December 31, 2021.