V.-10 21-1818 Ratification by the Board of Education of Agreement Between Owner and Contractor - District and Everlast Development Inc., Oakland, CA ("Contractor"), for the latter perform the Scope of Work consisting of but not limited to cut, remove, and properly dispose of vegetation ground fuels along the fence line; clear weeds throughout each entire school site, including playgrounds, trim bushes to an aesthetic design; trim back ivy and any protruding branches along fence line and low hanging tree branches; remove and haul all trash and debris, with all services fully compliant with the Oakland Fire Code and Standards, for the Kaiser Elementary School Vegetation Fire Management Project, in the amount of $24,500.00, which includes a contingency of $3,000.00, as the lowest responsive bidder, rejecting all bids, with the work anticipated to commence on July 26, 2021, and scheduled to last for thirty (30) days, with an anticipated ending of August 25, 2021.