Meeting Time: August 25, 2021 at 4:00pm PDT
The online Comment window has expired

Agenda Item

V.-12 21-1723 Approval by the Board of Education of Agreement Between Owner and Contractor by and between Bay Construction Company, Oakland, CA ("Contractor"), for the latter to provide Sewer Line Replacement, for the Skyline High School Project, as described in Article I of the Agreement, in the amount of $266,000.00, which includes a contingency of $25,000.00, as the lowest responsive bidder, and rejecting all other bids, if any, and authorizing the President and Secretary of the Board to sign the Agreement for same with said bidder with the work scheduled to commence on August 26, 2021, and scheduled to last for Sixty (60) Calendar days, ending October 24, 2021.