Meeting Time: June 23, 2021 at 4:00pm PDT
The online Comment window has expired

Agenda Item

V.-14 21-1368 Approval by the Board of Education of Change Order No. 1, Agreement by and between the District and Redgwick Construction Company, Oakland, CA, for a time extension only for the Horace Mann Elementary School Retaining Wall & Stair Replacement Project, due to weather delays, extending the term of the Agreement from December 10, 2020 through March 10, 2021 to July 31, 2021 (an additional 143 days). All other terms and conditions of the Agreement remain in full force and effect.