Meeting Time: October 14, 2020 at 4:00pm PDT
The online Comment window has expired

Agenda Item

T.-3 20-1693 Approval by the Board of Education of Resolution No. 2021-0082 - Emergency Construction, Futility of Bidding, and Approval Of Change Order for the Sherman Elementary School Site Storm Drain and Sewer Replacement Project to Bay Construction ("Contractor"), Oakland, CA, to provide a combination of additional construction services which consist of removing damaged asphalt, install new drainage system, replace fittings with cast iron and sewer clay piping, repair broken sections of pipes, in the amount of $99,600.00 and 52 calendar days, and authorizing the President and Secretary of the Board to sign the Change Order for same with said contractor. ___ 4/5 Vote Required