P.-2 20-0570 Approval by the Board of Education of Award of Agreement Between Owner and Contractor - Competitively Bid - to Bay City Engineering Company, Inc. ("Contractor"), Oakland, CA, for the latter to provide abatement and demolition of existing boiler and install two (2) Weil McLain Cast Iron Sectional Boilers 1378 MHP input, for the Melrose Leadership Academy Boiler Replacement Project, in the amount of $265,000.00,which includes a $30,000.00 contingency allowance, as the lowest responsive and responsible bidder, and rejecting all other bids, if any, and authorizing the President and Secretary of the Board to sign the Agreement for same with said bidder with work scheduled to commence on April 8, 2020, and scheduled to last for Ninety (90) Calendar days, and concluding July 7, 2020, pursuant to the Agreement.