Meeting Time: March 11, 2020 at 4:00pm PDT
Note: The online Request to Speak window has expired.
The online Comment window has expired

Agenda Item

P.-12 20-0528 Approval by the Board of Education of Award of Agreement Between Owner and Contractor- Non-Competitively Bid* - between District and Innovative Construction Company, Oakland, CA, for the latter to provide constructing improvements to include installation of weatherproofing windscreen Structural Framing Connections, for the Madison Park Academy Expansion Project, in the amount of $123,904.00, as the selected contractor, and authorizing the President and Secretary of the Board to sign the Agreement for same with said bidder with work scheduled to commence on March 12, 2020, and scheduled to last until December 31, 2020, pursuant to the contract. ___ *A fair, competitive Request for Proposal (RFP) selection process used.(Government Code 4529.10 et seq.)