K.-5 18-1005 Approval by the Board of Education of Resolution No. 1718-0138 - Award of Bid Agreement and Contract for Construction Services, on behalf of the District, to G & G Builders, Inc., Livermore, CA, for the Melrose Leadership Academy - Elementary Play Matting Replacement Project, in the amount of $155,457.00, as the lowest responsive, responsible bidder, and rejecting all other bids, if any, and authorizing the President and Secretary of the Board to enter into and execute an Agreement for same with the successful bidder with work being conducted in one (1) phase, with a Contract Duration: Sixty (60) Calendar Days, commencing August 23, 2018, and ending on October 31, 2018.