Agenda Item

K1.-1 18-0514 Approval by the Board of Education of Change Order No. 2 to Agreement between District and Arntz/Focon JV, Inc., to extend duration of project per construction schedule, delayed mostly by small change order work requested by District between December 23, 2016 to April 21, 2017, for Madison Park Academy Expansion, in an amount not to exceed $263,370.00, increasing the Contract not to exceed amount from $1,714,398.29 to $1,977,768.29.