Agenda Item
K.-9 17-2624 Approval by the Board of Education of Resolution No. 1718-0075, Award of Bid and Contract for Construction Services for the Frick ISS Synthetic Turf Project on behalf of the District to Redgwick Construction, Oakland, CA, in the amount of $1,005,400.00, as the lowest responsive, responsible bidder (with the alternate shade structure bid in the amount of $479,400.00 NOT awarded at this time) and rejecting all other bids, if any, and authorizing the President and Secretary of the Board to enter into and execute an Agreement for same with the successful bidder with work being conducted in one (1) phase, with a Contract Duration: (74) days Calendar Days, commencing January 11, 2018, and ending on July 1, 2018.