15-0436 Approval by the Board of Education of Resolution No. 1415-1082 - Award of Bid and Construction Contract between District and Strawn Construction, San Jose, CA, for the latter, as the lowest responsive, responsible bidder and rejecting all other bids, if any, to provide restoration of bleachers; construction of a new press box; remodel of student restrooms that includes removal/replacement of water closers, removal and replacement of toilet accessories, repair of wood roof deck, replacement of roofing, repair of fascia at eve, installation of additional door hardware in conjunction with the Fruitvale Bleachers/Restrooms Project for the period commencing March 25, 2015 and concluding no later than June 9, 2015 in the amount of $751,819.00.