14-2099 Approval by the Board of Education of Small Construction Contract between District and Gallagher and Burk, Inc., Oakland, CA, for the latter to provide layout, excavation, install new underground storm water lines and catch basins, test and roughly back fill; excavate materials to be stock piled on site and will be removed during new summers new asphalt replacement phase; this partial work is being coordinated with the different users at the warehouse yard to keep their activities operational, in conjunction with the 955 High Street Paving Project, more specifically delineated in the Scope of Services in Exhibit "A", incorporated herein by reference as though fully set forth, with work to be completed within one hundred twenty consecutive calendar days from the date specified in the District's Notice to Proceed, at for the period commencing October 22, 2014 and concluding no later than March 30, 2015 in an amount not to exceed $90,000.00.