Agenda Item

14-0837 Approval by the Board of Education of Change Order No. 1 to Construction Contract with McCarthy / Turner JV, Oakland, CA, for the latter to provide payments due to the Owners Contingency which was entirely absorbed during the course of construction due to unforeseen abatement, design changes, Owner requests and Agency requests in conjunction with the MetWest Educational Center Phase 2 Project in the additional amount of $1,500,000.00, increasing the Agreement from $35,865,425.00 to $37,365,426.00. All other terms and conditions of the Agreement remain in full force and effect.