Meeting Time: May 14, 2014 at 5:00pm PDT
The online Comment window has expired

Agenda Item

14-0834 Approval by the Board of Education of Resolution No. 1314-1025 - Award of Bid and Construction Contract between District and RF MacDonald, Hayward, CA, for the latter as the lowest responsive, responsible bidder and rejecting all other bids, if any, for replacement of the HVAC system in conjunction with the Fruitvale Elementary School HVAC Replacement Project, with project required to be completed within one hundred eighty-five (185) consecutive calendar days from the date specified in the District's Notice to Proceed (May 14, 2014 and concluding no later than November 27, 2014) in the amount of $71,500.00.